When a program is late, the usual instinct is to add people, and when it is important, the instinct is to start it with a large team. Both treat software delivery as a matter of volume, assuming that more hands produce more output. That assumption fails for work that is mostly design and decisions, as most large programs show when much of their calendar goes on alignment meetings and on waiting for other teams.
We should declare an interest. Farside is deliberately small and works in small senior teams, which means this article argues for the way we have chosen to operate and should be read skeptically. For the same reason we have set out where the argument fails, because a firm that only ever recommends its own shape is not giving advice.
By a small senior team we mean three to seven people, most of whom have already built comparable systems and run them, who between them hold every skill the work needs and who carry the outcome from design through to operation. Our claim is that for a bounded and difficult problem, a team like this usually delivers sooner and at lower total cost than a team several times its size, and leaves less to clean up afterwards.
In brief
- Coordination costs grow faster than headcount, so each person added to a team contributes less than the previous one and, beyond a certain size, slows the team down.
- Most of the effort in enterprise software goes into deciding what to build and how the parts fit together, and that work does not divide evenly among more people.
- Seniority matters because experienced engineers make fewer decisions that later have to be reversed, which has little to do with how fast anyone types.
- Small teams are a poor fit for work that is wide and separable, for operations that run around the clock, and for organizations that need to develop junior engineers.
- A small team works only when it has a narrow scope, direct access to the people who make decisions, and the authority to release.
Coordination grows faster than headcount
This arithmetic is old and still widely ignored. In a team of n people there are n(n-1)/2 possible pairs who may need to talk, which gives ten pairs for a team of five and one hundred and five for a team of fifteen. Not every pair will talk, but the relationships that must be kept in step multiply much faster than the people doing the work.
Fred Brooks described this in The Mythical Man-Month, together with the observation now known as Brooks's law, that adding people to a late software project makes it later. New people need time to learn the system, and they take that time from the people who already know it, and the work has to be divided again to make room for them.
Large teams usually respond by adding structure in the form of workstreams with leads and a program office that runs status reporting and dependency boards. Each is reasonable on its own, but together they amount to a second organization whose product is coordination, and a meaningful share of the most experienced people's time moves from the system to the structure.
The effect reaches the design as well. Conway's law, from Melvin Conway's 1968 paper, observes that organizations produce system designs that mirror their communication structures, so a program split into six teams tends to produce a system of six parts joined by interfaces even when the problem itself does not divide into six. A small team is free to let the architecture follow the problem.
Most of the work is making decisions
Much of the time in an enterprise system goes on questions of judgment. Someone has to work out what a business rule is when the two people who own it disagree, and someone has to discover that the customer identifier in the billing system differs from the one in the CRM. The team also has to decide what should happen when a downstream system is unavailable, and where a calculation belongs so that it is done only once.
Writing the code that follows from those decisions is the smaller and shrinking share of the effort. As discussed in AI coding assistants in the enterprise, tools that draft code move the constraint further toward judgment, meaning the ability to know what to ask for and to recognize a wrong answer, along with an understanding of how a change affects the rest of the system. This favors experienced people and weakens the case for staffing a team to produce volume.
What seniority buys
"Senior" is an overused label, so we should say what we mean by it. Years of service matter less than whether someone has taken a comparable system through production and lived with the consequences, which is what allows them to do the following.
- They recognize an expensive mistake before making it, such as a data model that cannot represent a refund, an integration built with no retry, or a batch job that will stop finishing once volumes grow.
- They can make a decision with incomplete information and write down why, which matters because large programs lose much of their time waiting for someone with the authority and confidence to decide.
- They hold the whole system in mind, so one person who understands the data, the application and the operations will notice a problem that three specialists would each consider someone else's.
- They talk to the business directly, without a relay through analysts and leads, so fewer requirements are lost on the way.
The combined effect is less rework, because a design mistake found in production costs far more to fix than one avoided at the whiteboard, and an experienced team avoids more of them. For the same reason daily rates are a misleading comparison, and the useful one is the total cost of reaching a working system, including the money spent undoing earlier decisions.
One pricing service, two team shapes
Consider a mid-size distributor that needs to replace the pricing logic buried in its ERP customizations with a service that the ERP, the web shop and the sales team's quoting tool can all call. The rules are complicated, covering customer-specific agreements, volume breaks and promotions, plus exceptions that only two people in the commercial team fully understand.
In the large shape, the work goes to a team of twenty-two: a program manager, two business analysts, an architect, three squads of five and a test team. The analysts interview the commercial team and write a requirements document, and the squads are divided into rules engine, integrations and user interface. For the first two months most of the effort goes on agreeing interfaces between squads and waiting for requirements sign-off. When integration starts in month five, the rules engine squad's model of a customer agreement turns out unable to handle agreements that span product groups, which the commercial team mentioned in an interview but the document summarized out, and the fix touches all three squads.
In the small shape, the work goes to five people: a principal who has built pricing systems before, three senior engineers, and one of the two commercial experts for half of each week. In the first fortnight they extract a year of real invoices and build a test set in which each case states the customer, product, quantity and date and the price charged, which becomes the definition of done. The cross-group agreements surface in week two as failing test cases, when changing the model still costs an afternoon. The ERP integration is built first and runs in shadow mode, calculating prices alongside the old logic and logging the differences, before anything is switched over.
The second shape works because the people who understand the problem and those who build the solution are in the same conversation, and because five people can change direction within a day. The measures would be the elapsed time to the first shadow-mode comparison, the number of price differences against the old system over time, and the share of the code rewritten after integration began. This is the pattern behind product engineering done with small teams and frequent releases.
Where the argument fails
A position is worth holding only with its limits stated, and these are the ones we recognize.
Work that is wide and separable, such as migrating four hundred reports, rolling a system out to sixty sites or converting a large estate of similar interfaces, is mostly volume once the pattern is set. A small senior team should establish the pattern and the tooling, and a larger team can then apply it.
Operations that run around the clock need enough people for a humane on-call rotation, and five people cannot sustain that indefinitely, however capable they are.
Key-person risk rises because a small team concentrates knowledge, so if two of five leave, much of the understanding goes too. The risk is reduced by discipline more than by headcount, through a written decision log, tests that encode the rules, runbooks and a deliberate transfer to the people who will own the system. We treat that transfer as part of the work, for the reasons argued in handover is the deliverable.
Developing people is beyond an organization staffed only with senior engineers, which has no way of producing the next ones. An entirely senior team suits a bounded, difficult build, whereas a permanent engineering organization needs a mix and needs its senior people to spend time teaching.
Many concurrent demands also exceed what one small team can handle, since it does one thing well. An enterprise with thirty stakeholders and twelve priorities needs either several small teams with clear boundaries or a larger structure.
What a small team needs from you
Small teams fail too, usually for reasons outside the team.
- A bounded outcome, meaning one use case in one system with one measurable result. A goal like "modernize the platform" describes a portfolio, which needs a diagnosis and a set of options before it needs a team.
- A decision maker within a day's reach, because the team can move only as fast as its questions are answered, and a sponsor who replies in a week sets the pace at a week.
- Access from the first week to the real data, the real systems and the people who do the work, since a month spent waiting for credentials removes much of the advantage.
- Authority to release, at least to a staging environment every week, without a separate approval chain for each release.
- Protection from the surrounding program, because if the five people must also attend every governance forum of a large program, the result is a large program with a small team inside it. Why programs drift that way is the subject of why transformation programs stall in their second year.
Questions to ask before you staff the next initiative
- Is the difficult part of this work deciding or doing? If it is mostly deciding, start small.
- What is the smallest group that holds every skill needed to take one slice to production?
- Who will answer the team's questions, and how quickly?
- Which parts become repetitive once a pattern exists, and when would more people actually help?
- How will knowledge get out of the team's heads into written records and tests, and who is being taught?
- If you are engaging outside help, who exactly will do the work, and are they the people you met? With a managed engineering team, ask for names and for the principal who is accountable.
The cheapest test of the argument is to take one stalled initiative, cut its scope to a single outcome and give it to five experienced people with a sponsor who answers the same day, then compare their result after twelve weeks with what the larger structure produced in its last twelve.