Cloud and infrastructure

Cloud migration

Your workloads running in their new environment, with the old environment switched off.

How we do it

Overview

A migration seldom goes wrong on the day of the move itself, and the trouble usually appears in the months before and after it. An undocumented dependency breaks a batch job two days after cutover, or an application that was fast in testing turns slow in production because its database stayed behind and every query now crosses a network link. The early waves tend to go smoothly while the last few systems prove awkward, and two years on the organization is still paying for the cloud and the data center at the same time.

We move one workload at a time, and each workload has its own plan covering what it depends on, how its data is copied and kept in sync, how the switch is made, how we confirm it worked and how we return if it did not. The rollback is rehearsed before the cutover, because a rollback that exists only on paper cannot be relied on. It also has an expiry, since once the new system has accepted writes the old one never saw, going back means losing that data or replaying it, and the plan states exactly when that point is reached.

From the first workload onward, infrastructure is written as code. An environment assembled by clicking through a console cannot be reviewed, rebuilt or copied for testing, so it turns into the next legacy estate running on newer hardware. The work finishes with decommissioning, which means servers wiped and removed, licenses and contracts ended and the facility handed back, and until that has happened the savings promised in the business case remain a forecast.

Challenges we address

The failures we are usually called in to fix
  1. Dependencies found during the cutover

    The inventory records servers but says nothing about how they talk to each other. A hard-coded address, a shared file mount, a license server or a nightly job on a forgotten machine comes to light only after the system it relied on has moved.

  2. A rollback plan that was never run

    The plan contains a single line saying 'revert to source'. Whether the old system can take traffic again, how long that would take and what would happen to orders written to the new database in the meantime have never been tested.

  3. Two environments running with no end date

    The straightforward workloads move in the first year, while the difficult ones, which are usually the oldest and most heavily connected, get pushed back from one wave to the next. As long as they remain, the data center cannot close and both sets of bills keep arriving.

  4. Servers copied with their problems intact

    Machines are replicated exactly as they are, unpatched, configured by hand and carrying years of undocumented changes. Because nothing about how the estate is built or deployed has changed, it is as hard to change as it was before, and it is now rented by the hour.

  5. Split applications that crawl

    An application is moved while its database waits for a later wave. Calls that took a fraction of a millisecond within one room now cross a wide-area link many times for every screen, and users tend to notice within the hour.

Our approach

How the work runs, in order
  1. Map what talks to what

    We capture network flows and process connections over a period long enough to include month-end and other infrequent jobs, and then check the resulting picture with each application owner. Workloads that depend closely on each other are grouped so that they move together and do not end up talking across a slow link.

  2. Build the target as code

    The landing environment for each wave is defined in infrastructure code, reviewed and deployed through a pipeline, and we prove that it works by destroying and rebuilding a non-production copy. Nothing is created by hand that a future engineer would later have to reverse-engineer.

  3. Rehearse cutover and rollback

    For every workload we carry out the move in a test environment using a copy of real data, which means replicating, switching and verifying, then rolling back and verifying again. From the rehearsal we get timings, a runbook and the point beyond which a rollback would lose data.

  4. Cut over and watch

    The cutover takes place in an agreed window with the owner present and a go or no-go checklist. Technical checks are backed by business checks such as placing an order, printing an invoice and matching a report, and the old system is left intact until the rollback window has closed.

  5. Switch the old one off

    After each wave we decommission whatever has moved, keeping final backups under your retention rules, wiping disks, removing hardware and ending licenses and support contracts. We treat the program as complete once the facility or the legacy platform is empty, and the go-live of the last workload is one step on the way there.

Technical capabilities

What we design, build and operate
  • Dependency discovery

    Flow capture, process mapping and interviews with owners turn a list of servers into move groups, and they pick up the batch jobs and file shares that inventories tend to miss.

  • Migration planning per workload

    For each workload we choose between rehosting, replatforming, refactoring, replacing and retiring, record the reason and the effort involved, and arrange the results into waves.

  • Infrastructure as code

    Networks, compute, databases and access are defined in version-controlled modules and deployed by a pipeline, which means every migrated environment can be reviewed, reproduced and rebuilt.

  • Database and data migration

    A bulk load followed by change data capture keeps source and target in sync until cutover, and row counts and checksums are compared before the switch is declared complete.

  • Selective containerization

    We package the applications that suit containers to run on Kubernetes or a managed container service, and we state clearly which applications would be better left on virtual machines.

  • Cutover engineering

    Runbooks carry timings measured in rehearsal, along with traffic switching through DNS or load balancers, verification scripts and a rollback path whose expiry is written down.

  • Data-center exit

    A decommissioning schedule linked to lease and contract dates covers data wiping, hardware disposal, circuit termination and the last few systems that would otherwise keep a facility open.

  • Identity and secrets migration

    Service accounts, certificates and stored credentials are moved into managed identity and a secrets manager, so that passwords kept in configuration files do not travel along with the servers.

Where it applies

Business applications
  • Data center exit against a lease date

    We work backward from the lease date to a wave plan, scheduling the hardest systems early enough that they cannot keep the building open.

  • Hardware at end of support

    Workloads are moved off servers or storage that the manufacturer has stopped supporting, which avoids buying replacement hardware for another cycle.

  • Leaving an aging virtualization platform

    When license terms or support for the current hypervisor change, virtual machines are relocated, and for each workload we decide whether it moves as a machine or as a container.

  • Moving between providers or regions

    Workloads are shifted from one cloud provider or region to another for reasons of cost, residency or consolidation, using the same method of rehearsal and rollback.

  • Carving out a business unit

    The systems of a unit being divested or acquired are separated into an environment of their own by a contractual date, and shared services are untangled as part of the work.

  • Database platform moves

    Databases are moved onto managed services, which can include a change of engine where licensing makes it worthwhile and the application's queries can be tested on the new engine.

In practice

Two situations this service is built for, and what we would do in each.

Logistics and supply chain

A distributor leaving its data center on a fixed date

The situation
A distribution company has given notice on its data center and has a firm date by which it must leave. Its warehouse management system, order processing and reporting all run there on virtual machines, next to older servers whose purpose is only partly known. Because the warehouses operate around the clock, there is no natural window for an outage.
What we would build
We would capture network flows over several weeks to learn what the unknown servers do and to group the systems that have to move together, and the target environment would be built as code. The cutover of the warehouse system would be rehearsed with replicated data until both the switch and the rollback fit within the quietest shift. Each wave would end with its source machines powered off and removed, tracked against the exit date.
What it is designed to change
The aim is to meet the exit date with the facility empty, so that it does not have to be extended for a handful of remaining systems. Progress would be tracked through the number of machines still powered on at the old site each week and whether each cutover finished inside its rehearsed window.
Education

A university moving enrollment systems between terms

The situation
A university runs its student records, enrollment and learning platforms on aging servers that the manufacturer no longer supports, and during enrollment week the load rises to many times its normal level. An earlier attempt to move the enrollment system was abandoned when a test cutover could not be reversed cleanly.
What we would build
We would plan the waves around the academic calendar and move low-risk systems first to prove the method. The enrollment database would be replicated continuously to the target, with record counts and checksums compared every day, and the full cutover and rollback would be rehearsed twice with registry staff running real enrollment checks. The new environment would be sized from the measured peak load and would scale down outside enrollment periods.
What it is designed to change
The enrollment system would move between terms with a rollback that has been shown to work. Success would mean that enrollment week runs on the new environment with no manual intervention and that the old servers are switched off before the next support renewal is due.

Technologies

We work in your stack and recommend on fit. We resell nothing.
Migration tooling
AWS Application Migration Service · Azure Migrate · Google Cloud Migration Center · AWS Database Migration Service · Azure Database Migration Service · Google Cloud Database Migration Service
Infrastructure as code
Terraform · OpenTofu · Pulumi · AWS CloudFormation · Bicep · Ansible
Containers and compute
Kubernetes · Amazon EKS · Azure Kubernetes Service · Google Kubernetes Engine · Amazon ECS · Azure Container Apps · Cloud Run
Data movement
native database replication · Debezium · AWS DataSync · AzCopy · Google Storage Transfer Service · rsync
Connectivity
AWS Direct Connect · Azure ExpressRoute · Google Cloud Interconnect · site-to-site VPN

Business outcomes

What changes for the organization
  • One environment to pay for

    Because the old platform has actually been closed, the savings in the business case show up on invoices and stop being a line in a forecast.

  • Cutovers the business barely notices

    Every move has been rehearsed and timed with real data, so the length of the window is known in advance and owners can check their own processes before it closes.

  • An estate that can be rebuilt

    Every migrated environment is defined in code, which means recovery, audits and new test environments can all start from a repository where they once depended on one engineer's memory.

  • No surprise two days later

    Dependencies are found by observing the systems before the move, so a forgotten batch job or shared folder appears in the plan well before it could cause an incident.

What you hold at the end

  • A dependency map and move groups confirmed by application owners
  • A wave plan sequenced against lease and contract dates
  • Infrastructure code for every migrated environment, in your repository
  • A rehearsed cutover and rollback runbook per workload
  • Data validation reports comparing source and target
  • A decommissioning record for every retired system
  • Operating runbooks handed to the team that takes over

Questions buyers ask

That depends on the deadline and on the workload. With a fixed exit date it is reasonable to move most systems largely as they are, as long as they are right-sized from measured usage and built as code when they arrive. Rewriting a system while moving it combines two risks, because when something breaks you cannot tell whether the move or the rewrite was the cause. We change what the move requires, such as hard-coded addresses or a switch to a managed database, and plan deeper modernization as separate work with its own tests.

Very few systems can tolerate no downtime at all, although many can tolerate only a little. We keep the source and target databases in sync through continuous replication, so the cutover becomes a short pause while the last changes arrive, followed by a switch of traffic and verification. Rehearsal shows how long that pause will be before the business is asked to agree to it. Where even a short pause is unacceptable, the application usually has to be changed to run in both places at once, which is a larger project that we scope separately.

It involves actually running it. During rehearsal we switch to the target and back again, then check that the source system serves users correctly, recording how long it took and who had to do what. We also define the point at which a rollback is no longer clean, since once the target has accepted new data, going back means replicating that data back or accepting its loss. The runbook gives that point as a time and names the person who makes the decision, and both are agreed before cutover night.

Not every workload is, because containers are worth the effort mainly for applications that are deployed often, scale horizontally and keep their state in a database or object store. A packaged application with an installer controlled by the vendor, software licensed to a specific host, or a stable system that changes twice a year gains little and takes on an extra operational layer. We containerize a workload where doing so shortens delivery or lowers its cost, and we leave the others on virtual machines or managed services.

A migration is finished when the source has been switched off and the contracts behind it have ended. We run decommissioning as a workstream of its own, with dates for the final backup, the data wipe, hardware removal and the termination of licenses and circuits. The stubborn systems are identified at the outset and scheduled early, since they determine whether the facility can close. If every workload is live but the old environment still draws power, the program is still running, and we report it that way.

Discuss cloud migration with the people who would do the work.

Tell us what you are trying to do and where it is stuck. A principal reads every message and replies within one working day.